Wednesday 18 February 2015

Site works halt 3 days into the build... We're off to a good start!

Many of the followers and regular visitors of this blog would know that our site works officially commenced exactly three days ago. You might also have noticed that after looking at our cut site that I had a bit of a hunch that something was not right. Well.. I was right.

After checking our final construction drawings yesterday I noticed that the floor level has been dropped by 200 mm from our contract drawings. This set off some alarms and I immediately proceeded to email my building coordinator and text my slab supervisor.

Unfortunately, that's all I could as it was after hours and that meant another sleepless night caused by our build. Being human, questions start to arise. Did I read the drawings correctly? Why did I miss this? Why did they do/miss this? etc...

This morning I waited anxiously for an email or phone call. That didn't happen. I wasn't going to wait as I knew I didn't have much time to react.

Finally, I managed to get through to my slab supervisor and building coordinator. After explaining the situation, they both agreed that they needed to look into this further and have called a meeting first thing tomorrow morning. Attendees will be our BC, SS and one more member in charge of siting and floor level designs at the PD Keilor office. Luckily, we all agreed that works will be stopped until this is rectified. I was very assertive about this as they had deviated from our contract drawings without any Building Variation (BV).

Since the site has been cut already, there are really only a few options that I can think of to rectify this (if they agree):

  1. Fill, compact and raise the platform for the slab
  2. Increase the thickness and in turn the height of the concrete floors
I would really appreciate some feedback of which would be the better solution of the two. Please comment or PM me if you can help. 


Thanks for reading and sorry about the essay!